Home  •  How the Transmission System Works  •  Webcast  •  Studies & Reports  •  Projects  •  Contact Us 
Planning Zones

Northwest Zone
Northeast Zone
West Central Zone
Twin Cities Zone
Southwest Zone
Southeast Zone

MN Counties (large map)

Sponsoring Utilities
American Transmission Company
Dairyland Power Cooperative
East River Electric Power Cooperative
Great River Energy
ITC Midwest
L&O Power Cooperative
Minnesota Power
Minnkota Power Cooperative
Missouri River Energy
Otter Tail Power Company
Rochester Public Utilities Commission
Southern Minnesota
Municipal Power Agency
Xcel Energy
Participating Government Agencies
Minnesota Public Utililities Commission
Minnesota Department of Commerce
Environmental Quality Board
Related Links
North American Electric Reliability Council
Midcontinent ISO
National Electric Safety Code
US Department of Energy
CapX2020.com

Studies and Reports > 2009 MN Biennial Report > Needs: Introduction


Transmission Projects Report 2009
Chapter 6: Needs: Introduction
 
pp. 34-36

6.0 Needs

6.1 Introduction

Chapter 6 contains a discussion of each of the present and reasonably foreseeable inadequacies that have been identified in the six transmission planning zones. The discussion for each zone begins with a table summarizing each inadequacy and a map showing the general location of each inadequacy. Then a table is presented that lists those inadequacies that were identified in previous biennial reports that have been addressed through the completion of a project, or perhaps through combination with another inadequacy. These tables are followed with a discussion of each inadequacy in the zone and, in most cases, a map showing the general location of the inadequacy. The following information describes the type of information that is presented for each inadequacy.

Tracking Number. The utilities developed a numbering system in the 2005 Report that is continued here. The numbering system has three parts to it: the year the inadequacy was reported, the zone in which it occurs, and a chronological number assigned in no particular order, starting with number one for each reporting year. Thus, the Tracking Number for inadequacies first identified in the 2009 Biennial Report will begin with 2009, followed by the zone, and followed by a number. Tracking Numbers beginning with other years means that that particular inadequacy was first identified in that year. For example, Tracking Number 2009-WC-N6 (the Elk River – Becker Area) is an inadequacy in the West Central Zone first identified in this report. Tracking Number 2007-SE-N1, (the overload of the Rochester to Adams 161 kV line) was first identified in the 2007 Report.

Utility. This category lists the utility or utilities that have the main responsibility for addressing the inadequacy. In some instances the local municipal utility or other entity that is primarily responsible for the inadequacy is not a transmission-owning utility that is required to file this biennial report, so the reporting utility with the most involvement with the project is identified.

Inadequacy. Minnesota Statutes § 216B.2425 – the statute requiring the filing of this biennial report – requires the utilities to identify “present and reasonably foreseeable future inadequacies in the transmission system in Minnesota.” Neither the statute nor the PUC rules define the term “inadequacy.”

Consistent with the statute and the PUC objective to identify those situations that may affect reliability of service, the utilities have for each Tracking Number included an entry describing the inadequacy that has been found. The inadequacy may be an overload of certain facilities in a contingency situation, it may be an interconnection request, it may be increasing demand, or it may be a combination of factors jeopardizing the reliability of the transmission infrastructure. An inadequacy may be identified through transmission planning, such as when the impact of contingency events are examined, or through the announcement of a new development, such as an ethanol plant or the proposed construction of a new generating facility, or through an increase in the demand for energy in a particular area.

For those inadequacies reported in prior years, the discussion in many cases is similar to the language from a previous biennial report because the inadequacy remains the same as was reported previously, although an update on the status of the matter is provided.

Alternatives. The statute requires the utilities to identify alternative means of addressing each inadequacy listed. Initially, the utilities engage in a preliminary screening analysis – a qualitative exercise relying on experience and judgment – to determine what alternatives are within the realm of possible solutions to the problem. It is common to look at both short-term and long-term options.

There are a number of general factors that are relied on to make this initial cut. For example, the utilities will favor a transmission alternative that does not involve the creation of new right-ofway, such as the reconductoring of an existing line, over one that requires additional easements or land for a new line or new generation. Obviously, the utilities are going to prefer alternatives that are less expensive than the more expensive solutions. It can cost upwards of $1500 per kilowatt to install generation. It is often readily apparent that a transmission option will be less expensive than a generation alternative. Sometimes transmission is the only option, such as when a new generating facility needs to connect to the grid.

Both the statutes (Minnesota Statutes § 216B.2426) and the PUC rules (Minnesota Rules part 7848.1300, item E) require the utilities to consider the possibility of installing distributed generation and other nontransmission alternatives, in addition to transmission solutions. The utilities have attempted to identify those situations in which a distributed generation option might be possible.

Analysis. The intent of this category is to summarize the information the utilities have compiled with respect to identifying the inadequacy and evaluating possible alternatives for addressing the situation. In some cases, studies have been completed or are underway and these studies can be consulted for more detailed information. Obviously, the farther out into the future an inadequacy needs resolving, the less detail there will be about various alternatives. In some cases the utility may have selected a preferred alternative and an explanation will be provided of why that alternative was selected.

Importantly, once the utility reaches the point where an alternative is selected and governmental approval is required before the project can be undertaken, the utility will examine all those alternatives that are required to be examined under the applicable requirements. Identifying a preferred alternative in the biennial report will often be the project that is ultimately implemented, but the analysis is not complete until the authorization is obtained.

Schedule. This category sets forth the utility’s best estimate on when certain steps will have to be taken to avoid or correct an inadequacy. In some cases, the timing of a solution may depend on developments in the future, like load growth or decisions by independent power producers, and the timing is uncertain. Also, it is not always possible to know whether a particular option will have to be reviewed and approved by the Public Utilities Commission, but the utilities have attempted to identify those projects that would require a Certificate of Need and a Route Permit from the Commission.

PUC Docket Numbers. If a decision has been made on a solution for a particular situation, and the project selected requires review and approval by the Public Utilities Commission and the Utility has applied for PUC approval, the PUC will have assigned a docket number to the utility’s request for approval. It is helpful to know the PUC Docket Number because that number can be used to review documents that are part of the administrative record in the matter. Click on

https://www.edockets.state.mn.us/EFiling/edockets/searchDocuments.do?method=showeDocketsSearch

and enter the docket number to find the complete record.

For nearly every Tracking Number, a map of the area is included following the discussion. For those Tracking Numbers where a route permit has been applied for, and a PUC Docket Number is provided, more specific maps showing proposed transmission line routes can be found in the PUC docket for that matter.

Completed Projects. At the beginning of each zone discussion, a table is presented that lists those projects that have been completed within the last two years, since the 2007 Report was prepared. Those Tracking Numbers in the table will not be reported upon in future biennial reports. If a particular project has been approved by the PUC or other regulatory body, but the construction is not complete, the matter is not listed in this table and the Tracking Number is reported on in the body of the report. In a few cases, projects are listed in this table not because they are complete, but because they have been combined with other Tracking Numbers and are reported with the other matter. The reader can refer to the other Tracking Number to read the full discussion of the closed matter.