Home  •  How the Transmission System Works  •  Webcast  •  Studies & Reports  •  Projects  •  Contact Us 
Planning Zones

Northwest Zone
Northeast Zone
West Central Zone
Twin Cities Zone
Southwest Zone
Southeast Zone

MN Counties (large map)

Sponsoring Utilities
American Transmission Company
Dairyland Power Cooperative
East River Electric Power Cooperative
Great River Energy
ITC Midwest
L&O Power Cooperative
Minnesota Power
Minnkota Power Cooperative
Missouri River Energy
Otter Tail Power Company
Rochester Public Utilities Commission
Southern Minnesota
Municipal Power Agency
Xcel Energy
Participating Government Agencies
Minnesota Public Utililities Commission
Minnesota Department of Commerce
Environmental Quality Board
Related Links
North American Electric Reliability Council
Midcontinent ISO
National Electric Safety Code
US Department of Energy
CapX2020.com

Studies and Reports > 2009 MN Biennial Report > NE Planning Zone > Needs: 6.3.11 Hubbard-Menahga Area

To inquire about this project, click here.


Transmission Projects Report 2009
Section 6.3: Northeast Zone
 
p. 107

6.3.11 Hubbard-Menahga Area

Tracking Number. 2007-NE-N3

Utility. Great River Energy

Inadequacy. The 34.5 kV system between Hubbard and Verndale is incapable of supporting the voltage on contingency for the projected load by 2010.

A map of the area is shown on the following page.

Alternatives. GRE is planning on constructing a 115 kV line between the radial Hubbard-Minnesota Pipeline 34.5 kV line and the Todd-Wadena Electric Cooperative Menahga substation. This line will be operated at 34.5 kV initially.

Analysis. The Menahga area sees low voltages on the loss of the Hubbard-Twin Lakes 34.5 kV line and the Leaf River area sees low voltages for loss of the Verndale source. Transferring the Menahga load from the Hubbard-Verndale system will rectify these low system voltages. Historical load levels indicate that low voltage is already a problem if this critical contingency were to occur.

115 kV transmission is proposed for this area as there is some wind potential along the corridor. The existing 34.5 kV system would not be able to serve the needs of a large wind farm in the area, due to capacity limitations on the system. The start of a 115 kV line between Hubbard and Wing River would provide the appropriate capability.

Schedule. GRE has scheduled this project for a 2013 energization. The proposed 115 kV line is not expected to exceed ten miles in length, which means that a Certificate of Need from the Public Utilities Commission will not be required.

 


Transmission Projects Report 2009
Section 6.3: Northeast Zone
 
p. 108

Click here or on map below to download high resolution PDF map.