Studies and Reports > 2011
MN Biennial Report > Biennial Report Requirements
|
Transmission
Projects Report 2011 |
Chapter 2: Biennial Report Requirements |
|
pp. 4-7 |
2.0 Biennial
Report Requirements
2.1 Generally
Minnesota Statutes §
216B.2425 requires any utility that owns or operates electric transmission
lines in Minnesota to submit a transmission projects report to the Minnesota
Public Utilities Commission by November 1 of each odd numbered year. The statute identifies a number of items
that are to be included in the report, primarily the identification and
analysis of present and reasonably foreseeable future inadequacies in the
transmission system.
The Minnesota Public
Utilities Commission (MPUC) has adopted rules that govern the content of the
transmission projects report and establish procedures for reviewing the
report. Those rules are codified in
Minnesota Rules chapter 7848. Over the years, in response to experiences with
the rule requirements, the PUC has modified the application of these rules in a
number of ways, including methods of soliciting public input and reporting on
transmission inadequacies. The utilities have followed the applicable
procedures and reporting requirements for each report.
In addition to the statute
and the rules, the Public Utilities Commission has over each reporting cycle
established specific requirements that utilities must address in the
report. For example, in response to
PUC direction, the 2009 Biennial Report contained a discussion of each
reporting utility’s transformer capability and the 2007 Biennial Report
identified the miles of transmission line owned by each utility. The PUC has also established specific
requirements for the 2011 Report, and these are discussed in the next section
below.
2.2 Specific Reporting Requirements for 2011
The Minnesota Transmission
Owners (MTOs) submitted the 2009 Biennial Report on November 1, 2009. The Public Utilities Commission afforded
interested persons an opportunity to submit comments regarding the completeness
of the Biennial Report. After considering all comments that were filed, on May
28, 2010, the Commission issued its Order Accepting Reports, Granting Variance,
and Setting Future Filing Requirements. PUC Docket No. E-999/M-09-602
One provision of the
Commission’s May 28, 2010, Order directs the reporting utilities to address
efforts the utilities have undertaken to solicit input on transmission planning
issues from the public and local government officials. The PUC directed the utilities to modify
the Internet site maintained by the utilities to report on transmission
planning efforts at:
http://www.minnelectrans.com
The utilities have reported
on their efforts in this regard in Chapter 4 of this report.
Another aspect of the
Commission’s Order relates to transmission planning. The Commission directed the utilities to
discuss in some detail how they conduct strategic planning and to identify
those projects that the utilities believe warrant designation as priority
projects. The utilities have
addressed this aspect of the Commission’s Order in Chapter 3. The Commission
specifically asked for discussion of the system
considerations that affect the timing of the Corridor Upgrade Project. This discussion is found in Chapter
8.
One continuing obligation
that has been required of the utilities since 2007 is to report on their status
with regard to compliance with Minnesota Renewable Energy Standards. In this report, as in the 2007 and 2009
reports, the utilities have provided a Gap Analysis showing their upcoming
needs for renewable energy to meet RES milestones. A Gap Analysis is an estimate of how
many more megawatts of renewable generating capacity a utility will require
beyond what is presently available to meet an upcoming RES milestone of a
certain percentage of retail sales from renewables. This Gap Analysis is found in Chapter
8.
One significant change
approved by the Public Utilities Commission for the 2011 Biennial Report is the
manner in which the utilities report on the transmission inadequacies that have
been identified. In past reports, all the information required for a particular
transmission inadequacy was contained in the Biennial Report. This year,
however, utilities that are members of the Midwest Independent Transmission
System Operator (MISO) will simply make reference to where in the annual report
prepared by MISO the information about a particular inadequacy can be found.
That annual report is called the MISO Transmission Expansion Planning (MTEP)
Report. The Commission determined that it was unnecessary to repeat in this
report the information that already is in the MTEP Report.
All transmission
owning members of MISO are obligated under the Transmission Owners
Agreement (TOA) they signed with MISO to participate in the MISO transmission
planning process. These planning obligations are detailed in the MISO Business
Practices Manual BPM-20 – Transmission Planning, and they require
similar information about planned projects that is required in this Biennial
Report. Any information required in this report that is not required in the
MTEP Report is now being added by the utilities to their project descriptions
in the MTEP Report. MISO has also agreed to add an additional data field to
their projects-reporting spreadsheet beginning with the MTEP12 Report to show
the unique “Tracking Number” from the biennial reporting process for each of
the MTO Minnesota projects.
For the 2011 Biennial Report, a cross reference table is provided to show where each
Tracking Number can be found in a MTEP report for projects identified by MISO
utilities.
A further explanation of the MTEP planning process and where
in the annual reports information about a particular transmission inadequacy
can be found is provided in Chapter 6. For those utilities that are not part of
MISO, full information about those utilities’ transmission inadequacies
continues to be found in this document.
2.3 Reporting Utilities
Minnesota Statutes §
216B.2425 applies to those utilities that own or operate electric transmission
lines in Minnesota. The PUC has
defined the term “high voltage transmission line” in its rules governing the
Biennial Report to be any line with a capacity of 200 kilovolts or more and any
line with a capacity of 100 kilovolts or more and that is either longer than
ten miles or that crosses a state line. Minn. Rules part 7848.0100, subp. 5. Each of
the entities that is filing this report owns and
operates a transmission line that meets the PUC definition. Information about
the utility and transmission lines owned by each utility is provided in Chapter
7 of this Report. In addition, a
contact person for each utility is included in Chapter 7.
The statute allows the
entities owning and operating transmission lines to file this report
jointly. The Minnesota Transmission
Owners (MTO) have elected each filing year to submit a
joint report and do so again with this report. The utilities jointly filing this report
are:
American Transmission Company, LLC
Dairyland Power Cooperative
East River Electric Power Cooperative
Great River Energy
Hutchinson Utilities Commission
ITC Midwest LLC
L&O Power Cooperative
Marshall Municipal Utilities
Minnesota Power
Minnkota Power Cooperative
Missouri River Energy Services
Northern States Power Company d/b/a Xcel Energy
Otter Tail Power Company
Rochester Public Utilities
Southern Minnesota Municipal Power Agency
Willmar Municipal Utilities
Of the above utilities, East River
Electric Power Cooperative, Hutchinson Utilities Commission, L&O Power
Cooperative, Marshall Municipal Utilities, Minnkota Power Cooperative, Rochester Public Utilities and Willmar Municipal Utilities
are not members of MISO; all the others are.
2.4 History of Biennial Reports
The Minnesota Legislature created the biennial reporting
requirement in 2001 when it adopted Minnesota Statutes § 216B.2425. The 2011 Biennial Report is the sixth
such report filed by the MTO. All of the Biennial Reports are available on the
webpage maintained by the utilities at:
http://www.minnelectrans.com
The Biennial Reports can also be found on the PUC edockets webpage using the Docket Number from the table
below. Visit:
https://www.edockets.state.mn.us/EFiling/edockets/searchDocuments.do?method=showeDocketsSearch
Biennial
Report |
PUC Docket
Number |
PUC Order |
2011 |
E-999/M-11-445 |
|
2009 |
E-999/M-09-602 |
May 28, 2010 |
2007 |
E-999/M-07-1028 |
May 30, 2008 |
2005 |
E-999/TL-05-1739 |
May 31, 2006 |
2003 |
E-999/TL-03-1752 |
June 24, 2004 |
2001 |
E-999/TL-01-961 |
August 29, 2002 |
2.5 Certification Requests
Minnesota
Statutes § 216B.2425, subd. 2, provides that a
utility may elect to seek certification of a particular project identified in
the Biennial Report. According to subdivision 3, if the Commission certifies
the project, a separate Certificate of Need (CON) under section 216B.243 is not
required.
On May 31, 2011, the MTO
advised the Commission that there would be no certification requests included
with the 2011 Biennial Report.
2.6 Renewable Energy Standards
The 2007 Biennial Report
included an entirely separate report called the Renewable Energy Standards
Report, which was required by the Legislature as part of the 2007 Renewable
Energy Act to be submitted to the Commission by November 1, 2007. This
requirement was a one-time obligation and the 2009 Biennial Report did not
include a separate RES Report. However, the 2009 Biennial Report did include a
Gap Analysis and a discussion of various studies that were underway related to
transmission needs related to renewable energy.
The Public Utilities
Commission has directed the MTO to continue to address in the Biennial Report
transmission issues relating to meeting the RES milestones. Thus, the 2011 Biennial Report also
contains a Gap Analysis and a discussion of ongoing transmission studies that
affect the utilities’ abilities to obtain necessary amounts of renewable
energy. This analysis and discussion are found in Chapter 8.
|